The gravel haul is currently in Division 4, south of HWY 14.

Spring Dust Control is still being applied for residents who submitted applications for April 15 and currently is in Division 4. Main collector roads will be completed when residents are done.

TWP 492 road construction – 1 mile complete of 5 miles.

TWP 512 chip seal application – 2nd application to be completed this week – weather permitting.

Culvert repair and/or replacement is ongoing throughout the County.