Construction update:

First coat of chip seal have been completed on TWP 480. Contractor has moved onto second coat on RR 203. Will complete the second lift of chip seal on TWP 480 at the end of this week (weather permitting).

Shoulder pulls are ongoing on TWP 500

Maintenance update:

Grader operators are continuing blading and maintaining roads.

Gravel Haul from the Viking gravel pit to the Ryley gravel pit is now complete.

Bridge replacement on RR 163 has tentatively been scheduled to begin on October 4th.

 

 