< Back to Road Matters & More

Task

Start Date

Working Days

Projected

End Date

Update – August 8

Culvert Maintenance

Apr 24

135

Oct 30

 

Twp 492 Terracem

Jun 11

15

Jun 29

Terracem is complete; 2nd lift of chip seal to be applied by mid-August

Rge 201 Terracem

Jul 2

2

Jul 3

Terracem is complete; 2nd lift of chip seal to be applied by mid-August

Twp 510 Terracem

Jul 4

5

Jul 10

Terracem is complete; 2nd lift of chip seal to be applied by mid-August

Twp 512 Terracem

Jul 12

5

Jul 18

Terracem is complete; 1st lift of chip seal to be applied by mid-August

Reg 191 Terracem

Jul 19

2

Jul 20

Terracem is complete; 1st lift of chip seal to be applied by mid-August

Patching Oil

Jul 23

10

Aug 3

Expected completion by August 31

Oiling (TBD)

Aug 7

14

Aug 24

 

Bridge Construction

Rge 184, between Twp 494 and Twp 500

Aug 15

61

Oct 15

 

Patching/Shoulder Pulls

Aug 28

24

Sep 30

 

Backsloping- TBD

Oct 2

21

Oct 31

 

Gravelling

Apr 24

112

Sep 28

 

Dust Control- 1st Application

May 22

22

Jun 22

Complete

Dust Control- 2nd Application

Jul 30

14

Aug 18

 

Schedule is subject to change depending on the weather.