Task

Start Date

Projected

End Date

Update – August 15

Culvert Maintenance

Apr 24

Oct 30

 

TWP RD 492 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Jun 11

Aug 31

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – ECD – Mid August

RGE RD 201 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Jul 2

Aug 31

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – ECD – Mid August

TWP RD 510 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Jul 4

Aug 31

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – ECD – Mid August

TWP RD 512 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Jul 12

Aug 31

Phase 1 – Complete

Phase 2 – ECD – Mid August

Phase 3 – ECD – Mid August

RGE RD 191 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Jul 19

Aug 31

Phase 1 – Complete

Phase 2 – ECD – Mid August

Phase 3 – ECD – Mid August

Patching Oil

Jul 23

Aug 3

Expected completion by August 31

Oiling RR 202

Aug 13

Aug 17

 

TWP RD 512 TerraCem 2nd location

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Aug 20

Aug 31

Phase 1 – ECD -  Aug 24

Phase 2 – ECD – Mid Sept

Phase 3 – ECD – Mid Sept

TWP RD 482 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Sept 4

Sept 28

Phase 1 – ECD - Sept 20

Phase 2 – ECD -  End of Sept

Phase 3 – ECD – End of Sept

Patching/Shoulder Pulls

Aug 28

Sep 30

 

Backsloping- TBD

Oct 2

Oct 31

 

Gravelling

Apr 24

Sep 28

 

Dust Control- 1st Application

May 22

Jun 22

Complete

Dust Control- 2nd Application

Jul 30

Aug 18

Complete

Schedule is subject to change depending on the weather.
**ECD – Estimated Completion Date