Twp 500 shoulder pull ongoing, expected completion day July 15
Terracem in Islet Lake Estates  is complete, tack coat to be applied before July 15
Terracem preparation on Spilstead Road (1 mile) to commence July 13, terrace application to begin July 18 (weather permitting)
Rge rd 144 south of Hwy 14 (4 miles) shoulder pull to commence July 18, (weather permitting)
Patching NW of Tofield (Twp 512) is ongoing

 