2018 Construction Schedule Updated
Task |
Start Date |
Working Days |
Projected End Date |
Update – August 8 |
||
Culvert Maintenance |
Apr 24 |
135 |
Oct 30 |
|
||
Twp 492 Terracem |
Jun 11 |
15 |
Jun 29 |
Terracem is complete; 2nd lift of chip seal to be applied by mid-August |
||
Rge 201 Terracem |
Jul 2 |
2 |
Jul 3 |
Terracem is complete; 2nd lift of chip seal to be applied by mid-August |
||
Twp 510 Terracem |
Jul 4 |
5 |
Jul 10 |
Terracem is complete; 2nd lift of chip seal to be applied by mid-August |
||
Twp 512 Terracem |
Jul 12 |
5 |
Jul 18 |
Terracem is complete; 1st lift of chip seal to be applied by mid-August |
||
Reg 191 Terracem |
Jul 19 |
2 |
Jul 20 |
Terracem is complete; 1st lift of chip seal to be applied by mid-August |
||
Patching Oil |
Jul 23 |
10 |
Aug 3 |
Expected completion by August 31 |
||
Oiling (TBD) |
Aug 7 |
14 |
Aug 24 |
|
||
Patching/Shoulder Pulls |
Aug 28 |
24 |
Sep 30 |
|
||
Backsloping- TBD |
Oct 2 |
21 |
Oct 31 |
|
||
Gravelling |
Apr 24 |
112 |
Sep 28 |
|
||
Dust Control- 1st Application |
May 22 |
22 |
Jun 22 |
Complete |
||
Dust Control- 2nd Application |
Jul 30 |
14 |
Aug 18 |
|
Schedule is subject to change depending on the weather.