2021 Construction Schedule

Posted on

Schedule is subject to change depending on the weather.

**ECD – Estimated Completion Date        TBD – To Be Determined

TASK

START DATE

PROJECTED END DATE

UPDATE – MAY 19

TWP RD 480 TerraCem

from HWY 36 to RGE RD 132

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

May 25

 

 

 

May 31

 

 

 

 

 

Phase 1 –

Phase 2 –

Phase 3 –

Phase 4 –

RGE RD 132 TerraCem

from TWP RD 480 to P&H entrance

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

June 1

 

 

 

June 7

 

 

 

 

 

Phase 1 –

Phase 2 –

Phase 3 –

Phase 4 –

RGE RD 132 TerraCem REPAIRS

from P&H north to TWP RD 482

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

June 8

 

 

 

June 10

 

 

 

 

 

Phase 1 –

Phase 2 –

Phase 3 –

Phase 4 –

TWP RD 482 TerraCem REPAIRS

from TWP RD 482 to HWY 36

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

June 11

 

 

 

June 14

 

 

 

 

 

Phase 1 –

Phase 2 –

Phase 3 –

Phase 4 –

TWP RD 512 TerraCem

from RGE RD 191 to RGE RD 195

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

June 21

 

 

July  13

 

 

 

 

Phase 1 –

Phase 2 –

Phase 3 –

Phase 4 –

RGE RD 202 TerraCem

from TWP RD 504 to TWP RD 510

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

July 19

 

 

July  28

 

 

 

 

Phase 1 –

Phase 2 –

Phase 3 –

Phase 4 –

Road Rehabilitation Project

Shoulder Pulls (Contractor)

Aug 16

Sept 20

 

Culvert Maintenance

Apr 19

Nov 1

Ongoing

Road Oiling (location TBD)

Aug 3

Aug 20

 

Patching Oil Roads

May 3

Sept 27

Ongoing

Patching/Shoulder Pulls (location TBD)

Sept 7

Oct 8

 

Backsloping- TBD

Oct 12

Nov 1

 

Gravelling

Feb 3

Sept 28

Ongoing

Dust Control - 1st Application

May 3

May 21

 

Dust Control - 2nd Application

Aug 3

Aug 13