2020 Construction Schedule

Schedule is subject to change depending on the weather.

**ECD – Estimated Completion Date        TBD – To Be Determined

TASK

START DATE

PROJECTED END DATE

UPDATE – September 9

RGE RD 182 TerraCem (from TWP RD 494 north to bridge 3 miles)

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

June 8

 

 

 

June 19

 

 

 

 

 

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – Complete

Phase 4 –

BRUCE 1st Ave between Queen and Main Street - TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

June 22

 

 

 

June 23

 

 

 

 

 

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – Complete

Phase 4 –

BRUCE Queen Street between 1st

and 2nd Ave - TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

June 24

 

 

 

June 25

 

 

 

 

 

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – Complete

Phase 4 –

BRUCE 2nd Ave between HWY 857 and Main Street - TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

June 29

 

 

 

July 2

 

 

 

 

 

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – Complete

Phase 4 –

RGE RD 145 between Hwy 14 & TWP RD 484 - TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

July 6

 

 

July  7

 

 

 

 

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – Complete

Phase 4 –

TWP RD 514 between

RGE RD 193 – 195 - TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

July 8

 

 

July  17

 

 

 

 

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – Complete

Phase 4 –

Gravelock – (location TBD)

July 6

July 23

 

Culvert Maintenance

Apr 20

Nov 1

Ongoing

Road Oiling (location TBD)

July 27

Aug 14

 

Patching Oil Roads

May 4

Oct 31

Ongoing

Patching/Shoulder Pulls (location TBD)

Sept 3

Oct 4

 

Backsloping- TBD

Oct 7

Nov 1

 

Gravelling

Feb 3

Sept 28

Ongoing

Dust Control - 1st Application

May 26

June 3

Complete

Dust Control - 2nd Application

Aug 7

Aug 10

Complete

 