Task |
Start Date |
Projected End Date |
Update – August 15 |
||
Culvert Maintenance |
Apr 24 |
Oct 30 |
|
||
TWP RD 492 TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) |
Jun 11 |
Aug 31 |
Phase 1 – Complete Phase 2 – Complete Phase 3 – ECD – Mid August |
||
RGE RD 201 TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) |
Jul 2 |
Aug 31 |
Phase 1 – Complete Phase 2 – Complete Phase 3 – ECD – Mid August |
||
TWP RD 510 TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) |
Jul 4 |
Aug 31 |
Phase 1 – Complete Phase 2 – Complete Phase 3 – ECD – Mid August |
||
TWP RD 512 TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) |
Jul 12 |
Aug 31 |
Phase 1 – Complete Phase 2 – ECD – Mid August Phase 3 – ECD – Mid August |
||
RGE RD 191 TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) |
Jul 19 |
Aug 31 |
Phase 1 – Complete Phase 2 – ECD – Mid August Phase 3 – ECD – Mid August |
||
Patching Oil |
Jul 23 |
Aug 3 |
Expected completion by August 31 |
||
Oiling RR 202 |
Aug 13 |
Aug 17 |
|
||
TWP RD 512 TerraCem 2nd location Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) |
Aug 20 |
Aug 31 |
Phase 1 – ECD - Aug 24 Phase 2 – ECD – Mid Sept Phase 3 – ECD – Mid Sept |
||
TWP RD 482 TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) |
Sept 4 |
Sept 28 |
Phase 1 – ECD - Sept 20 Phase 2 – ECD - End of Sept Phase 3 – ECD – End of Sept |
||
Patching/Shoulder Pulls |
Aug 28 |
Sep 30 |
|
||
Backsloping- TBD |
Oct 2 |
Oct 31 |
|
||
Gravelling |
Apr 24 |
Sep 28 |
|
||
Dust Control- 1st Application |
May 22 |
Jun 22 |
Complete |
||
Dust Control- 2nd Application |
Jul 30 |
Aug 18 |
Complete |
Schedule is subject to change depending on the weather.
**ECD – Estimated Completion Date