Construction Schedule Update

Posted on

2018 Construction Schedule

Schedule is subject to change depending on the weather.

**ECD – Estimated Completion Date

TASK

START DATE

PROJECTED END DATE

UPDATE – AUGUST 24

Culvert Maintenance

Apr 24

Oct 30

 

TWP RD 492 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Jun 11

Aug 31

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – ECD – Mid August

RGE RD 201 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Jul 2

Aug 31

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – ECD – Mid August

TWP RD 510 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Jul 4

Aug 31

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – ECD – Mid August

TWP RD 512 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Jul 12

Aug 31

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – ECD – Mid August

RGE RD 191 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Jul 19

Aug 31

Phase 1 – Complete

Phase 2 – Complete

Phase 3 – ECD – Mid August

TWP RD 512 TerraCem 2nd location

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Aug 20

Aug 31

Phase 1 – Complete

Phase 2 – ECD – Mid Sept

Phase 3 – ECD – Mid Sept

TWP RD 482 TerraCem

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

Sept 4

Sept 28

Phase 1 – ECD - Sept 20

Phase 2 – ECD -  End of Sept

Phase 3 – ECD – End of Sept

Bridge Construction

   RGE RD 184 between

   TWP RD 494 and TWP RD 500

Aug 15

Oct 15

Bridge will be closed to public traffic during construction

Oiling RR 202

Aug 13

Aug 17

Completed

Patching Oil

Jul 23

Aug 3

Expected completion by August 31

Patching/Shoulder Pulls

Aug 28

Sep 30

 

Backsloping- TBD

Oct 2

Oct 31

 

Gravelling

Apr 24

Sep 28

 

Dust Control- 1st Application

May 22

Jun 22

Complete

Dust Control- 2nd Application

Jul 30

Aug 18

Complete