2019 Construction Schedule
Schedule is subject to change depending on the weather.
**ECD – Estimated Completion Date TBD – To Be Determined
TASK |
START DATE |
PROJECTED END DATE |
UPDATE – Aug 7 |
TWP RD 514 RoadTek Repairs |
May 21 |
June 3 |
Completed – May 23 |
TWP RD 512 east of SH 630 Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
May 21 TBD |
June 1 TBD |
Phase 3 – Completed May 27 Phase 4 – Complete May 31 |
TWP RD 482 west of HWY 36 Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
May 21 TBD |
June 1 TBD |
Phase 3 – Completed May 23 Phase 4 – Completed May 31 |
RGE RD 132 south of TWP RD 482 Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
May 21 TBD |
June 1 TBD |
Phase 3 – Completed May 23 Phase 4 – Completed May 31 |
RGE RD 182 TerraCem (from TWP RD 484 to Black Nugget Entrance) Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
Jun 3
|
July 31
|
Phase 1 – Completed June 15 Phase 2 – Completed June 18 Phase 3 – ECD – TBD Phase 4 – ECD – TBD |
TWP RD 502 TerraCem (from RGE RD 201 – 205) Phase 1 (Cement & Tack)
Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
Jul 2
|
Aug 31
|
Phase 1 - 205-204- cemented/tacked - 204-203 -cemented/tacked - 203-202 -cemented/tacked - 202-201 -cemented/tacked Phase 2 – Completed July 26 Phase 3 – ECD – TBD Phase 4 – ECD – TBD |
RGE RD 124 Gravelock (from TWP RD 470 – 463) Phase 1 (Soil Stabilization) |
Aug 6 |
Aug 16 |
Phase 1 – ECD – Mid August |
Bridge Construction TWP RD 494 west of SH 857 |
Sept |
Oct |
Bridge will be closed to public traffic during construction |
Culvert Maintenance |
Apr 22 |
Nov 1 |
Ongoing |
Road Oiling (location TBD) |
Aug 19 |
Aug 30 |
|
Patching Oil Roads |
Apr 15 |
Oct 31 |
Ongoing |
Patching/Shoulder Pulls |
Sept 3 |
Sept 24 |
|
Backsloping- TBD |
Oct 7 |
Oct 18 |
|
Gravelling |
Jan 23 |
Sept 27 |
|
Dust Control- 1st Application |
May 6 |
May 31 |
Complete |
Dust Control- 2nd Application |
Aug 6 |
Aug 9 |
|