2019 Construction Schedule

Schedule is subject to change depending on the weather.

**ECD – Estimated Completion Date        TBD – To Be Determined

TASK

START DATE

PROJECTED END DATE

UPDATE – Aug 7

TWP  RD 514 RoadTek Repairs

May 21

June 3

Completed – May 23

TWP RD 512 east of SH 630

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

 May 21

TBD

June 1

TBD

 

Phase 3 – Completed May 27

Phase 4 – Complete May 31

TWP RD 482 west of HWY 36

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

May 21

TBD

June 1

TBD

 

Phase 3 – Completed May 23

Phase 4 – Completed May 31

RGE RD 132 south of TWP RD 482

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

May 21

TBD

June 1

TBD

 

Phase 3 – Completed May 23

Phase 4 – Completed May 31

RGE RD 182 TerraCem (from TWP RD 484 to Black Nugget Entrance)

   Phase 1  (Cement)

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

Jun 3

 

 

 

July  31

 

 

 

 

 

Phase 1 – Completed June 15

Phase 2 – Completed June 18

Phase 3 – ECD – TBD

Phase 4 – ECD – TBD

TWP RD 502 TerraCem (from RGE RD 201 – 205)

   Phase 1  (Cement & Tack)

 

 

 

 

   Phase 2  (1st lift of chip seal)

   Phase 3  (2nd lift of chip seal)

   Phase 4 (Final sweep of chips)

Jul 2

 

 

 

 

 

 

Aug 31

 

 

 

 

 

 

 

 

Phase 1

- 205-204- cemented/tacked

- 204-203 -cemented/tacked

- 203-202 -cemented/tacked

- 202-201 -cemented/tacked

Phase 2 – Completed July 26

Phase 3 – ECD – TBD

Phase 4 – ECD – TBD

RGE RD 124 Gravelock (from TWP RD 470 – 463)

   Phase 1  (Soil Stabilization)

Aug 6

Aug 16

 

Phase 1 – ECD – Mid August

Bridge Construction

   TWP RD 494 west of SH 857

Sept

Oct

Bridge will be closed to public traffic during construction

Culvert Maintenance

Apr 22

Nov 1

Ongoing

Road Oiling (location TBD)

Aug 19

Aug 30

 

Patching Oil Roads

Apr 15

Oct 31

Ongoing

Patching/Shoulder Pulls

Sept 3

Sept 24

 

Backsloping- TBD

Oct 7

Oct 18

 

Gravelling

Jan 23

Sept 27

 

Dust Control- 1st Application

May 6

May 31

Complete

Dust Control- 2nd Application

Aug 6

Aug 9

 