< Back to Road Matters & More
2020 Construction Schedule
Schedule is subject to change depending on the weather.
**ECD – Estimated Completion Date TBD – To Be Determined
TASK |
START DATE |
PROJECTED END DATE |
UPDATE – June 10 |
RGE RD 182 TerraCem (from TWP RD 494 north to bridge 3 miles) Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
June 8
|
June 19
|
Phase 1 – Phase 2 – Phase 3 – Phase 4 – |
BRUCE 1st Ave between Queen and Main St - TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
June 22
|
June 23
|
Phase 1 – Phase 2 – Phase 3 – Phase 4 – |
BRUCE Queen St between 1st & 2nd Ave - TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
June 24
|
June 25
|
Phase 1 – Phase 2 – Phase 3 – Phase 4 – |
BRUCE 2nd Ave between HWY 857 and Main St. - TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
June 29
|
July 2
|
Phase 1 – Phase 2 – Phase 3 – Phase 4 – |
RGE RD 145 between Hwy 14 and TWP RD 484 - TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
July 6
|
July 7
|
Phase 1 – Phase 2 – Phase 3 – Phase 4 – |
TWP RD 514 between RGE RD 193 – 195 - TerraCem Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
July 8
|
July 17
|
Phase 1 – Phase 2 – Phase 3 – Phase 4 – |
Gravelock – (location TBD) |
July 6 |
July 23 |
|
Culvert Maintenance |
Apr 20 |
Nov 1 |
Ongoing |
Road Oiling (location TBD) |
July 27 |
Aug 14 |
|
Patching Oil Roads |
May 4 |
Oct 31 |
Ongoing |
Patching/Shoulder Pulls (location TBD) |
Sept 3 |
Oct 4 |
|
Backsloping- TBD |
Oct 7 |
Nov 1 |
|
Gravelling |
Feb 3 |
Sept 28 |
Ongoing |
Dust Control - 1st Application |
May 26 |
June 3 |
|
Dust Control - 2nd Application |
Aug 7 |
Aug 10 |
|