Construction Schedule
2021 Construction Schedule
Schedule is subject to change depending on the weather.
**ECD – Estimated Completion Date TBD – To Be Determined
TASK |
START DATE |
PROJECTED END DATE |
UPDATE – JUNE 9 |
TWP RD 480 TerraCem from HWY 36 to RGE RD 132 Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
May 25
|
May 31
|
Phase 1 – Complete Phase 2 – Phase 3 – Phase 4 – |
RGE RD 132 TerraCem from TWP RD 480 to P&H entrance Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
June 1
|
June 7
|
Phase 1 – Complete Phase 2 – Phase 3 – Phase 4 – |
RGE RD 132 TerraCem REPAIRS from P&H north to TWP RD 482 Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
June 8
|
June 10
|
Phase 1 – Phase 2 – Phase 3 – Phase 4 – |
TWP RD 482 TerraCem REPAIRS from TWP RD 482 to HWY 36 Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
June 11
|
June 14
|
Phase 1 – Phase 2 – Phase 3 – Phase 4 – |
TWP RD 512 TerraCem from RGE RD 191 to RGE RD 195 Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
June 21
|
July 13
|
Phase 1 – Phase 2 – Phase 3 – Phase 4 – |
RGE RD 202 TerraCem from TWP RD 504 to TWP RD 510 Phase 1 (Cement) Phase 2 (1st lift of chip seal) Phase 3 (2nd lift of chip seal) Phase 4 (Final sweep of chips) |
July 19
|
July 28
|
Phase 1 – Phase 2 – Phase 3 – Phase 4 – |
Road Rehabilitation Project Shoulder Pulls (Contractor) |
Aug 16 |
Sept 20 |
|
Culvert Maintenance |
Apr 19 |
Nov 1 |
Ongoing |
Road Oiling (location TBD) |
Aug 3 |
Aug 20 |
|
Patching Oil Roads |
May 3 |
Sept 27 |
Ongoing |
Patching/Shoulder Pulls (location TBD) |
Sept 7 |
Oct 8 |
|
Backsloping- TBD |
Oct 12 |
Nov 1 |
|
Gravelling |
Feb 3 |
Sept 28 |
Ongoing |
Dust Control - 1st Application |
May 3 |
May 21 |
Complete |
Dust Control - 2nd Application |
Aug 3 |
Aug 13 |
|