Update from Public Works 05.26.15
Prep for 492 is almost complete – cementing will start June 1
-Road bans will be set up during construction as well as for after the cement is down to allow time to set
Calcium has moved into Division 3. Dust control should be completed by the first week in June – weather permitting
Shoulder pull on RR 134 North of HWY 26 is being completed
Camp Lake fencing repairs will be completed this week
Patching of oiled roads