Update from Public Works - 06.19.14
-Terracem work (cementing) has been completed on the Camp Lake Road; the prime coat was applied June 17.
-TWP Rd 470 Terracem work (cementing) began June 18.
-Weather permitting, the 2014 Dust Control Program will be completed by June 24.
-Culvert repairs and installs, as well as approach work, is ongoing.
-Regular maintenance of oiled and gravel roads continues.
For more information, please call Public Works at 780-663-3730.