2018 Beaver County Construction Schedule
Task |
Start Date |
Duration |
Working Days |
End Date |
Culvert Maintenance |
Apr 24 |
|
135 |
Oct 30 |
Patching Oil |
May 7 |
|
24 |
Jun 8 |
TWP 492 Terracem |
Jun 11 |
|
15 |
Jun 29 |
Rge 201 Terracem |
Jul 2 |
|
2 |
Jul 3 |
Twp 510 Terracem |
Jul 4 |
|
5 |
Jul 10 |
Twp 512 Terracem |
Jul 12 |
|
5 |
Jul 18 |
Reg 191 Terracem |
Jul 19 |
|
2 |
Jul 20 |
Patching Oil |
Jul 23 |
|
10 |
Aug 3 |
Oiling (TBD) |
Aug 7 |
|
14 |
Aug 24 |
Patching/Shoulder Pulls |
Aug 28 |
|
24 |
Sep 30 |
Backsloping- TBD |
Oct 2 |
|
21 |
Oct 31 |
Gravelling |
Apr 24 |
|
112 |
Sep 28 |
Dust Control- 1st Application |
May 22 |
|
22 |
Jun 22 |
Dust Control- 2nd Application |
Jul 30 |
|
14 |
Aug 18 |
* Town of Tofield's Rge 191 July 23 - 27 (tentative) |
Thank you for your patience and understanding during construction season. Please be advised the speed limit is 50 km/hr unless otherwise posted. The work is scheduled to take place weather permitting.