Construction Schedule - July 17

Posted on

TerraCem Construction Postponed

Due to unforeseen circumstances, the Terra-Cem construction project in Beaver County is currently on hold. We understand the impact this may have on our community and are committed to keeping everyone informed. We will provide an update once we can begin scheduling work again.

Note: this does not affect the chip seal phases of construction, please see chip seal updates.

Chip Seal Construction Update

To receive 1st chip seal:

  • Rge Rd 161A between Hwy 14 & Hwy 855

To receive 2nd chip seal:

  • TWP RD 490 from RGE RD 124 to RGE RD 120
  • Rge rd 120 between Twp 490 & just north of colony entrance.
  • 49 Street in Holden
  • TWP RD 492 from RGE RD 172 – 190
  • HWY 854 from HWY 14 to TWP RD 500
  • TWP 480 from HWY 36 – RR 130
  • P&H Road TWP 480 up RR 130 to 482

There will be many loose rocks after the second chip seal layer is applied and speed limits will continue to be reduced on these roads until the final sweep is complete.

During this construction period, parts of the road may be closed for crew safety. Please use alternative routes; detours will be clearly marked. If you must drive through construction zones, proceed with caution (local traffic only). Beaver County's goal is to provide a healthy, injury free work environment for all employees, contractors, visitors and general public. Already this year we have had people exceeding the posted speed limit through our construction zones, endangering staff, contractors and the public.

There are potential hazards to the public and vehicles during the construction process. This can include heavy machinery, dust or mud, road material such as gravel, asphalt coatings and rock chips.

We apologize for the inconvenience that road maintenance and upgrading causes, but the same roads that receive the most traffic also need the most maintenance. Thank-you for your patience and understanding during construction. If you have any questions, please call the Beaver County Service centre at 780-663-3730.

 

2024 Construction Schedule
All dates weather dependent

Task

Start Date

End Date

Update - June 19

Culvert Maintenance

Apr 1

Nov 1

Ongoing

Patching oil roads throughout the season

May 1

Sep 29

Ongoing

Terra-Cem

     

Twp 490 between Rge rd 124 & Rge rd 120

May 13

May 31

 

Phase 1  (Cement) 
Phase 2 (1st lift of chip seal)
Phase 3 (2nd lift of chip seal)
Phase 4 (Final sweep of chips)

   

Phase 1 - Complete
Phase 2 - Complete
Phase 3 -
Phase 4 -

Rge rd 120 between Twp 490 & just north of colony entrance.

May 28

May 31

 

Phase 1  (Cement) 
Phase 2 (1st lift of chip seal)
Phase 3 (2nd lift of chip seal)
Phase 4 (Final sweep of chips)

   

Phase 1 - Complete
Phase 2 - Complete
Phase 3 -
Phase 4 -

Holden streets.

Jul 2

Jul 4

 

Phase 1  (Cement) 
Phase 2 (1st lift of chip seal)
Phase 3 (2nd lift of chip seal)
Phase 4 (Final sweep of chips)

   

Phase 1 - Complete
Phase 2 - Complete
Phase 3 -
Phase 4 -

Rge rd 161A between Hwy 14 & Hwy 855

Jul 5

Jul 9

 

Phase 1  (Cement) 
Phase 2 (1st lift of chip seal)
Phase 3 (2nd lift of chip seal)
Phase 4 (Final sweep of chips)

   

Phase 1 - Complete
Phase 2 -
Phase 3 -
Phase 4 -

Rge rd 200 between Hwy 630 & Park entrance

Jul 11

Jul 21

 

Phase 1  (Cement) 
Phase 2 (1st lift of chip seal)
Phase 3 (2nd lift of chip seal)
Phase 4 (Final sweep of chips)

   

Postponed until further notice

Rge rd 202 between Twp 502 & Twp 504

Jul 30

Aug 8

 

Phase 1  (Cement) 
Phase 2 (1st lift of chip seal)
Phase 3 (2nd lift of chip seal)
Phase 4 (Final sweep of chips)

   

Postponed until further notice

Rechip 2 miles TBD (Contracted for late summer)

Aug 12

Aug 23

 
Pavement Overlay      
RGE RD 205 from TWP RD 510 to south County border Jul 3 Jul 19 RGE RD 205 -

TWP RD 510 from HWY 833 to RGE RD 201

Jul 3 Jul 19 TWP RD 510 - 

Shoulder Pulls

Aug 1

Oct 2

 

Shoulder pull Rge rd 202 between Twp 502 & Twp 504.

 

 

Postponed until further notice

Backsloping  (location TBD)

Oct 2

Nov 1

 

Gravelling

Mar 13

Dec 22

Ongoing

Dust Control- 1st Application

May 1

May 19

Complete

Dust Control- 2nd Application

Aug 8

Aug 15